Smithfield Biosciencs, Inc. Form 483, December 2025

FDA issued this Form 483 to Smithfield Biosciencs, Inc. in Cincinnati, Ohio (FEI 1527761) at the end of a drug inspection that ended December 23, 2025. It lists 6 observations. FDA classified the inspection Official Action Indicated (OAI).

A Form 483 lists the investigators' observations at the end of an inspection. It is not FDA's final determination.

Source: FDA's Electronic Reading Room, posted Jul 27, 2026. Form 483 PDF on fda.gov. FDAgent is independent of FDA.

Inspection ended
Dec 23, 2025
Drugs · Drug Quality Assurance
FDA's outcome
OAI
Official Action Indicated
Posted by FDA
Jul 27, 2026
216 days after the inspection
Facility
FEI 1527761
Cincinnati, Ohio

The 6 observations on this Form 483

Read from the FDA-posted Form 483 PDF by OCR. FDAgent keeps an observation only when it matches the scanned text; check the PDF before quoting. The short titles are FDAgent's.

  1. 1

    Inadequate process validation for critical parameters

    Process Validation performed does not demonstrate that critical process parameters produce consistent APIs meeting their specifications and quality. Specifically, Your firm's process validation for (b) (4) USP, (b) (4) product codes, does not include validation of processing times listed in the batch record and in procedure SOP# 149. For example, (b) (4) (b) (4) (b) (4) cycle minimum times in the batch record were not tested, function was not monitored or recorded, maximum and minimum loads are not defined for stress testing the process, and (b) (4) being held throughout the cycle is not monitored. In addition, your firm manually switches cycle (b) (4) (b) (4) and (b) (4) operation rather than using recipes for repeatability. Your firm processed product code batches and (b) (4) product code batches during process validation due to various significant deviations and OOS results, such as product Color, atypical Loss on Drying, Total Plate Count failures, and other issues. This caused your firm to make additional batches in order to achieve process validation criteria of three consecutive product batches meeting specification. Your firm has released approximately (b) (4) out of (b) (4) out of batches of product code produced in the past two years and [illegible] batches of (b) (4) product code produced in the past two years. In addition, your firm's procedure, SOP# 149, "Operating the (b) (4)" states to (b) (4) Your firm does not document or review (b) (4) (b) (4) to confirm it approaches maximum low. In addition, your firm halts (b) (4) (b) (4) to check for product appearance to be (b) (4) cycles during (b) (4) On 11/04/2025, during (b) (4) USP, lot (b) (4) your firm halted the (b) (4) cycle from approximately 11:00am to 01:59pm to check for product appearance to be (b) (4) Your firm [illegible] until 11/6/2024 at 8:15am. resumed the cycle and continued (b) (4)

  2. 2

    Inadequate supplier qualification and material verification

    Supplier qualification do not include evaluations that provide adequate evidence that the manufacturer can consistently provide material meeting specifications Specifically, A.) Your manufacturer of (b) (4) has stated that "This product is unsuitable for use in the production of APIs as (b) (4) do not follow required GMP practices and do not sell pharmaceutical grade products". You proceeded to qualify this manufacturer of (b) (4) without obtaining a COA listing the identification and quantitation of all impurities as per the USP requirements. Additionally, you did not conduct a risk assessment to determine if this product would affect the quality of the final product. B.) Your firm has not completed additional testing of (b) (4) per USP standards at appropriate intervals since 2021 to assure that the manufacturer can consistently provide (b) (4) meeting specifications. C.) Your supplier of (b) (4) has not provided comprehensive certificates of analysis per USP requirements for every shipment/lot of (b) (4) received since 2021 and your firm has not checked and verified the reliability of certificates of analysis at regular intervals.

  3. 3

    Inadequate review and control of records

    Batch records and laboratory records of critical steps are not reviewed and approved by the quality unit appropriately. Specifically, A.) Your analytical laboratory paper records do not include signature and date of the second person reviewing (b) (4) (b) (4) impurity data on HPLC-1 for batches (b) (4) These batches were later released by QA without investigating whether they were reviewed or not. In addition, your firm does not include an electronic signature of review for HPLC data. B.) Your microbiology laboratory paper records do not include the signature of the second person reviewing the record for accuracy including for growth promotion studies and finished product testing. C.) (b) (4) used in production of (b) (4) USP does not have user login and parameters on the (b) (4) can be changed by anyone with access to the room. Non-production personnel such as engineering, regulatory affairs, and quality assurance can access these controls. In addition, without user login there is no electronic traceability of operators performing manual cycle switches. D.) (b) (4) contain a shared administrator password for all users. This causes there to be no electronic traceability of operators performing manual cycle switches.

  4. 4

    Failure to thoroughly investigate discrepancies and OOS

    ***REPEAT OBSERVATION FROM FDA 2019 INSPECTION*** Failure to conduct thorough investigations into unexplained discrepancies and the failure of a batch to meet any of its specifications. Specifically, A.) Your complaint investigation #137 for an additional doublet peak in the NMR spectra around (b) (4) ppm has not been thoroughly investigated. The identity of this peak has not been identified to date and retrospective analysis of previous NMR results data was not conducted. B.) Your firm failed to positively identify "black specks" that were found in (b) (4) lots (b) (4) Your firm performed FTIR testing on the substance and no peaks were obtained. Your quality unit failed to get a positive identification on the "black specks". (b) (4) (b) (4) and released on 12/16/2025. batches were reprocessed into (b) (4) was rejected. C.) In October 2024, your firm recorded two out-of-specification (OOS) results for Limit of (b) (4) in batches (b) (4) (b) (4) in Batch (b) (4) was retested twice, and the OOS result was confirmed on both occasions. Batch (b) (4) was retested six times, with the OOS result confirmed in each retest. As the OOS results were confirmed for both batches, they were deemed unsuitable for release, and Quality Assurance determined that the batches required reprocessing. This decision included batch (b) (4) which was being reprocessed during the week of 12/15/2025 into (b) (4) Your firm did not identify a root cause for the OOS results associated with these batches.

  5. 5

    Inadequate personnel and noncompliant laboratory equipment

    There is an inadequate number of personnel to manufacture and test APIs adequately. Specifically, Your firm is using equipment that does not have audit trail capabilities and unique logins: A.) Your firm currently uses GC-8A by Shimadzu which utilizes printed chromatograms and has no unique logins for analysts. Your firm has purchased a new GC-8860 by Agilent approximately 5 years ago, qualified the GC in April 2023, but have not started utilizing the new equipment due to resources being limited with turnover of key quality personnel. B.) Your firm is utilizing a UV-Vis that is not capable of audit trail review or unique logins for analysts. Your firm qualified a new UV-Vis in January 2025, however, you have not started testing with this equipment due to validation needing performed. Your firm's Regulatory Affairs and Laboratory Managers stated that this was also delayed due to turnover of key quality personnel.

  6. 6

    Stability program not followed annually

    The stability program to justify assigned expiration or retest dates is not followed. Specifically, Your firm has not placed any (b) (4) USP (b) (4) batches on stability in 2024 or 2025. In accordance with your approved stability procedure SOP 021 Stability Testing of Bulk Drug Substances, Rev. S, Effective Date 12/22/2020, at least one batch per year is required to be put on stability. In 2024, (b) (4) USP (b) (4) batches, were released and in 2025 batches of (b) (4) USP, (b) (4) were released.

Ask FDAgent about this Form 483

FDAgent reads the 483, the facility's inspections, warning letters and FDA's citations and answers in plain English, with links to the records.

Edit it or ask as written. 3 questions free, no card needed.

About this data

  • The PDF and its dates come from FDA's Electronic Reading Room, last synced Nov 23, 2026, 04:33 UTC; the inspection, its outcome and FDA's citations from FDA's Data Dashboard.
  • The observations are the text FDAgent read from this PDF by OCR, shown only when every printed observation passed FDAgent’s checks against the scanned text.
  • FDAgent leaves out the names of the people the Form 483 is addressed to and of the investigators.
  • FDAgent is independent of FDA.